DJC Build were engaged to carry out a variety of civil works including the installation of new PCU units, drilling of 1600 pier holes and trenching / backfilling across 2 x 5.25 MW solar farms. The project was located at the Gove mining lease, following an agreement with Gumatj and Rirratjingu traditional owner groups.


This Project aims to save the local power station approximately 20% on diesel consumption. DJC Build completed works under accelerated timeframes to meet client requirements and our team worked to strict safety and quality requirements, exceeding on all project outcomes.